Our Company was originally incorporated as `Regal Resources Private Limited', at Kolkata as a private limited company under the Companies Act, 1956 and received a certificate of incorporation issued by the RoC on January 02, 2012. Subsequently, pursuant to a special resolution passed by the Shareholders of our Company on October 10, 2015, the name of our Company was changed to `Regaal Resources Private Limited' and a fresh certificate of incorporation dated October 26, 2015 was issued to our Company by the RoC. Thereafter, our Company was converted into a public limited company pursuant to a special resolution passed by the Shareholders of our Company on November 10, 2021 and the name of our Company was changed to `Regaal Resources Limited' and a fresh certificate of incorporation dated March 30, 2022 was issued to our Company by RoC.
Major Events and Milestones: 2018 - Commencement of operation with an installed capacity of 180 TPD. - Installation of 1.3 MW Turbine
2022 - Increase in the installed capacity to 330 TPD. - Installation of further 2.5 MW Turbine (Taking total capacity to 3.8 MW). - Construction of raw material warehouse of 21,528 square feet with capacity of 4,000 metric ton
2024 - Increase in the installed capacity to 650 TPD. - Installation of further 3.3 MW Turbine (Taking total capacity to 7.1 MW)
2025 - Increase in the installed capacity to 750 TPD - Construction of 3 additional humidity controlled silos with individual capacity of 10,000 tons.
|